Start date:
May 2025
-
Completion date:
June 2025
Cowra, New South Wales
Cowra Shire Council
$450k
Water Reticulation Infrastructure, Remote & Regional Works, Road Under boring

Grace Williams
Project Manager
Cowra Shire Council required a Design and Construct Potable pipeline upgrade for exiting mains. Council has identified the need to replace an existing pipeline along the Comerford St and Lachlan St the existing fibro main is well past its life with continual mains breaks and needs urgent replacement. There are connections to existing rising mains, and 15 existing metered service lines along the alignment including connection to Weeroona Retirement Village, mainline line connections crossing Redfern St (RMS Road) will require under boring. All pipelines are to be kept in service throughout the works and transferred to the proposed new pipeline as part of the commissioning of the works.