Lachlan Shire Council

Condobolin Bore Fields Scheme

Project Timeframe

Start date:

July 2025

-

Completion date:

January 2026

Project Address

Lachlan Valley Way - Condobolin

Client Name

Lachlan Shire Council

Project Value

$4.20m

Key Components

Water supply Infrastructure, Remote & Regional Works, Pump Station Works

Project Contacts

Dynamic Content Image

John Bevan

Public Works

Dynamic Content Image

Mark Eastwood

Public Works

Dynamic Content Image

Shaula Siregar

Council Representative

Project Overview

Condobolin is the main township in Lachlan Shire Council, located in the Central West region of NSW.

Situated between Lake Cargelligo and Forbes, approximately 450 km from Sydney, it is a major service centre with a population of about 3,700. The township is easily accessible via four major roads: the Newell Highway, Kidman Way, Mitchell Highway and Lachlan Valley Way.

The Council proposed to construct an alternative raw water supply that will provide a reliable water source to the Condobolin Township especially during drought conditions. This source will be from two bores PB-2 and PB-3 that have already been constructed within the road reserve of the Lachlan Valley Way. The boreholes are approximately 430m apart.

The project was undertaken through funding made available through NSW Water Security for regions program.

Works Undetaken

The Works under the project are for the construction of two high flow ground water bore pumps, DICL discharge manifolds and pipelines to deliver raw water to a Balance Tank at a transfer pump station to service the proposed raw water main from Bore field to Condobolin. The Works include, but are not limited to:

The DN200 ductile above ground piping at PB-3 will connect below ground to the DN375 mPVC rising main with a DN375 DI junction at Chainage 2.03. Similarly, the DN200 ductile above ground piping at PB-2 will connect below ground to the DN375 mPVC rising main with a DN375 DI WYE at Chainage 430m. From that point, a single DN375 mPVC rising main will be laid and connected to the existing DN375 mPVC rising main to deliver the raw water to a balance tank at a transfer pump station site. The bore pumps will not work together but separately in a duty/standby configuration with each pump delivering a minimum flow rate of 86L/s at 55m Head pressure. In between PB2 and PB 3 sites, two Switch rooms, a backup Generator and the Main Switchboard will be located.

Bore No PB-2 Bore Pump & Manifold description.

We will Install the Submersible pump and motor that can supply a duty of 86l/s at 55mrts, this pump duty has been calculated as a worst-case scenario and with the Bore Level transducer fitted this pump can be slowed down to your required flow or increased to a maximum flow of around 85l/s. The pump will be suspended on 152mm Crusader Flexible bore column which will have enough room outside the hose coupling to allow for the motor cable and level transducer to pass without causing any cable damage, bore column centralisers will be installed at the bore pump and the bore head to eliminate any possibility of cable rubbing on the bore casing, once the column leaves the ground there will be a Stainless Steel Bore Cap assembly which will adapt to the 200mm Cast iron manifold this manifold includes Air Valve assembly, Swing Check Valve, flushing Valve, dismantling joint and a NMI approved Water Meter before going back into the ground and connecting to the 375mm Series 2 PVC Mainline which will run to the Balance Tank, The Bore Head Manifold assembly will be supported by Stainless steel stands and Base Pad as per drawing and photo supplied.

Bore PB-2 Bore Pump & Material list.

  • Pump Type - KSB 300-370 UPA 10” 3 Stage (316 Cast Stainless Steel)
  • Pump Material - Cast Stainless Steel 316
  • Number of Stages - 3
  • Duty Point - 83l/s Head 55m
  • Pump Efficiency -83%
  • Motor - 75kw Full Stainless Steel 316
  • Bore Column – 50mrts x 150mm Crusader Lay flat Pump column and Coupling connectors.
  • Electrical Cable -60mrts x 50mm Shielded Rubber insulated Submersible Electrical drop Cable.
  • 1 x Vega Bore Level Transducer
  • 1 x 400mm Stainless Steel Bore Head assembly
  • 1 x 200mm Cast iron Manifold

Bore PB-3 Bore Pump & Manifold description.

We will Install the Submersible pump and motor that can supply a duty of 83l/s at 55mrts, this pump duty has been calculated as a worst-case scenario and with the Bore Level transducer fitted this pump can be slowed down to your required flow or increased to a maximum flow of around 85l/s. The pump will be suspended on 152mm Crusader Flexible bore column which will have enough room outside the hose coupling to allow for the motor cable and level transducer to pass without causing any cable damage, bore column centralisers will be installed at the bore pump and the bore head to eliminate any possibility of cable rubbing on the bore casing, once the column leaves the ground there will be a Stainless Steel Bore Cap assembly which will adapt to the 200mm Cast iron manifold this manifold includes Air Valve assembly, Swing Check Valve, flushing Valve, dismantling joint and a NMI approved Water Meter before going back into the ground and connecting to the 375mm Series 2 PVC Mainline which will run to the Balance Tank, The Bore Head Manifold assembly will be supported by Stainless steel stands and Base Pad as per drawing and photo supplied.

Bore PB-3 Pump & Material list.

  • Pump Type - KSB 300-370 UPA 10” 3 Stage (316 Cast Stainless Steel)
  • Pump Material - Cast Stainless Steel 316
  • Number of Stages - 3
  • Duty Point - 83l/s Head 55m
  • Pump Efficiency -83%
  • Motor - 75kw Full Stainless Steel 316
  • Bore Column – 50mrts x 150mm Crusader Lay flat Pump column and Coupling connectors.
  • Electrical Cable -60mrts x 50mm Shielded Rubber insulated Submersible Electrical drop Cable.
  • 1 x Vega Bore Level Transducer
  • 1 x 400mm Stainless Steel Bore Head assembly
  • 1 x 200mm Cast iron Manifold

Pump Electrical System

  • Design supply and install Electrical Cable runs from both bore sites to the Electrical Switchboard including Pump Motor cabling Variable Speed Pump drives to interface with councils clear Scada control system to monitor bore water depths and current and cumulative flow rates to council WTP.
  • The bore field pumps are 75 kW motors and will be VSD controlled, based on advice from Council it is understood that a maximum of two bore pumps are proposed, these have been incorporated into the MCC design including the ability of having both operating concurrently.
  • The electrical design incorporates I/O for electrical instrumentation as identified in the functional specification including flow meters, pressure transducers and security reed switches at access doors.
  • Design supply and install Electrical pump shed Switchboard and Motor control centre including Variable Speed Pump drives to interface with councils clear Scada control system to monitor bore water depths and current and cumulative flow rates to council WTP.
  • Testing and Commissioning

Civil Construction Works

  • Supply and install all the necessary concrete slabs for erection of the Generator and Main
  • Switchboard rooms for the pump station above ground pipe network supports as specified.
  • Supply and install all the necessary hard stand areas including the bitumen seal road and
  • concrete road from the Lachlan Valley Way up to the sites and the earthworks around the sites
  • Supply and install a man-proof site security fence complete with gates for each site.
  • Supply, install, test and commission a 150kva backup diesel generator set located in between the bore sites.
  • Construct electrical Switch rooms for both PB2 & PB3 pump stations.
  • Metal security cage for generator and power distribution board.
  • Site works including earthworks, roadworks, drainage & water, power supply, and other works as deemed necessary.
  • Level 1 Electrical works -consisting of 3km overhead feed line to 2 x 315kva Transformers and 3300mrts of underground cabling to both pump sites.
  • Carry out all temporary works such as traffic management, environmental management, site establishment and disestablishment.

Highlights and Key Risks

  • Infield modifications to adapt to council requirements.

  • Ongoing discussions with council to improve the water supply system

  • Long electrical cable runs from bore sites to main switch room site.

  • Level 1 Electrical works and High Voltage Overhead Power Lines

  • Major Pump and Electrical construction in regional area

  • All subcontractors on the project were local to the region