Start date:
July 2025
-
Completion date:
January 2026
Lachlan Valley Way - Condobolin
Lachlan Shire Council
$4.20m
Water supply Infrastructure, Remote & Regional Works, Pump Station Works

John Bevan
Public Works

Mark Eastwood
Public Works

Shaula Siregar
Council Representative
Condobolin is the main township in Lachlan Shire Council, located in the Central West region of NSW.
Situated between Lake Cargelligo and Forbes, approximately 450 km from Sydney, it is a major service centre with a population of about 3,700. The township is easily accessible via four major roads: the Newell Highway, Kidman Way, Mitchell Highway and Lachlan Valley Way.
The Council proposed to construct an alternative raw water supply that will provide a reliable water source to the Condobolin Township especially during drought conditions. This source will be from two bores PB-2 and PB-3 that have already been constructed within the road reserve of the Lachlan Valley Way. The boreholes are approximately 430m apart.
The project was undertaken through funding made available through NSW Water Security for regions program.
The Works under the project are for the construction of two high flow ground water bore pumps, DICL discharge manifolds and pipelines to deliver raw water to a Balance Tank at a transfer pump station to service the proposed raw water main from Bore field to Condobolin. The Works include, but are not limited to:
The DN200 ductile above ground piping at PB-3 will connect below ground to the DN375 mPVC rising main with a DN375 DI junction at Chainage 2.03. Similarly, the DN200 ductile above ground piping at PB-2 will connect below ground to the DN375 mPVC rising main with a DN375 DI WYE at Chainage 430m. From that point, a single DN375 mPVC rising main will be laid and connected to the existing DN375 mPVC rising main to deliver the raw water to a balance tank at a transfer pump station site. The bore pumps will not work together but separately in a duty/standby configuration with each pump delivering a minimum flow rate of 86L/s at 55m Head pressure. In between PB2 and PB 3 sites, two Switch rooms, a backup Generator and the Main Switchboard will be located.
We will Install the Submersible pump and motor that can supply a duty of 86l/s at 55mrts, this pump duty has been calculated as a worst-case scenario and with the Bore Level transducer fitted this pump can be slowed down to your required flow or increased to a maximum flow of around 85l/s. The pump will be suspended on 152mm Crusader Flexible bore column which will have enough room outside the hose coupling to allow for the motor cable and level transducer to pass without causing any cable damage, bore column centralisers will be installed at the bore pump and the bore head to eliminate any possibility of cable rubbing on the bore casing, once the column leaves the ground there will be a Stainless Steel Bore Cap assembly which will adapt to the 200mm Cast iron manifold this manifold includes Air Valve assembly, Swing Check Valve, flushing Valve, dismantling joint and a NMI approved Water Meter before going back into the ground and connecting to the 375mm Series 2 PVC Mainline which will run to the Balance Tank, The Bore Head Manifold assembly will be supported by Stainless steel stands and Base Pad as per drawing and photo supplied.
We will Install the Submersible pump and motor that can supply a duty of 83l/s at 55mrts, this pump duty has been calculated as a worst-case scenario and with the Bore Level transducer fitted this pump can be slowed down to your required flow or increased to a maximum flow of around 85l/s. The pump will be suspended on 152mm Crusader Flexible bore column which will have enough room outside the hose coupling to allow for the motor cable and level transducer to pass without causing any cable damage, bore column centralisers will be installed at the bore pump and the bore head to eliminate any possibility of cable rubbing on the bore casing, once the column leaves the ground there will be a Stainless Steel Bore Cap assembly which will adapt to the 200mm Cast iron manifold this manifold includes Air Valve assembly, Swing Check Valve, flushing Valve, dismantling joint and a NMI approved Water Meter before going back into the ground and connecting to the 375mm Series 2 PVC Mainline which will run to the Balance Tank, The Bore Head Manifold assembly will be supported by Stainless steel stands and Base Pad as per drawing and photo supplied.
Infield modifications to adapt to council requirements.
Ongoing discussions with council to improve the water supply system
Long electrical cable runs from bore sites to main switch room site.
Level 1 Electrical works and High Voltage Overhead Power Lines
Major Pump and Electrical construction in regional area
All subcontractors on the project were local to the region